|
TOCC Project Game: does
task duration variability “average out?”
Games can be an effective vehicle for testing
and illustrating concepts. By building representative assumptions into a
simplified model the impact of individual factors can be tested and
evaluated.
One of the fundamental realities in managing projects is uncertainty. It can take different forms in
reality (work content may change, scope can vary, tasks may be longer—or
shorter—than expected, or resources might not be available when needed), but
it is a fact in most projects. The project plan in the
exercise below contains three simple assumptions:
-
Task dependencies (some must be done prior to others)
-
Task duration
variability (there is an average time, which in reality may be longer or
shorter)
-
Resources work
multiple tasks (some resources need to perform more than one task on the
same project)
The game will test the impact
variability (both task duration and resource dependency) has on the overall
project delivery.
Game Description
Below is a simple PERT chart of a project. Each task is done by a resource
identified by color. Each will on average take 7 days to complete. The task
dependencies are represented in the layout of the chart: Task 1 must be
completed before Task 3 can begin, Task 2 must be completed before Task 4
can begin, and both Task 3 and Task 4 must be done prior to starting
Task 5. There is only one resource of each color type so a task cannot begin
until the resource is available (e.g. Task 1 and Task 3 cannot be in-process
at the same time because they need the same resource, blue).

To play the game, roll two dice to determine the actual duration
of each task (the average roll—task duration—is 7, but the actual can be
anywhere between 2 and 12). Fill in the durations on a scorecard like the
one below, until all five tasks are complete.
|
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
27 |
|
Task
1
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Task 2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Task 3
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Task 4
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Task 5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Example: the first roll is a 6, second roll (task 2) is a 9, third roll
(task 3) is 4… Note that Task 3, though sequentially after Task 1, cannot
start until the red resource is finished with Task 2 and available.
Try it a couple of times to get a statistical sample of results, each
iteration should take only a few minutes. When you complete the game
click
here to see a discussion of the outcome and some conclusions we can apply
back to reality.
|